Cable route construction and high-voltage cable installation AI

TEDAS your procurement assistant

Ask a question about this procurement

t

Subject of the procurement

  • Objective: Construction of a cable route and installation of high-voltage cables at the Auvere plant territory (gas production unit ASU-2).
  • Technical requirements:
    • Connection of a 6 kV cable line (switchgear AC11 and substation ASU-2).
    • Route length: 1250 m.
    • Total length of cables: 8220 m (6 cables with a length of 1370 m each).
    • Cable type: NA2XS(F)2Y 01X500/35 12/20 kV BK.
    • Installation: Cable ladders…
       
      To see full summary, please log in or register.
t

👋 Hello! I am TEDAS – your procurement assistant 💼✨

What would you like to know about this procurement?

Note: This is preliminary information. For accuracy, please review all procurement documents.
Ask your questions here...

311414_hindamiskriteeriumid.pdf

311414_korvaldamise_alused_ja_kvalifitseerimistingimused.pdf

311414_Tehniline ülesanne.docx

311414_Tehniline ülesanne koos lisaga.zip

311414_Töövõtulepingu vorm.docx

311414_Töövõtulepingu vorm koos lisadega.zip

311414_tutvumisvisiidi info.docx

311414_vastavustingimused.pdf

311414.zip

Eesti Energia kontserni koostööpartnerite isikuandmete töötlemise põhimõtted.pdf

Eesti Energia kontserni partnerite eetikakoodeks (21.11.2022).pdf

Eesti Energia TTO nouded.pdf

Juhised pakkujatele väikehankemenetluses RHR.docx

Juhised pakkujatele väikehankemenetluses RHR.zip

Läbirääkimiste läbiviimise kord väikehankemenetluses ja lihthankemenetluses.docx

Liisuheitmise_kord RHR.docx

Tööandjate vastutuse ja kohustuste jaotus töötervishoiu ja tööohutuse tagamisel.pdf

Toovotulepingu-uldtingimused-EST_09.02.26.pdf

TÜ Lisa 1. Asendiplaan.pdf

Vorm 1 Pakkumuse vorm.xlsx

Vorm 2 Lepingute nimekiri.docx

Ready to get started?

Subscribe and enjoy all the benefits every day!