Reconstruction of the residual biogas combustion unit AI

TEDAS your procurement assistant

Ask a question about this procurement

t

Procurement object

  • Goal: Complete reconstruction of the wastewater treatment plant (WWTP) residual biogas combustion unit.
  • Scope of work:
    • Dismantling of three old residual biogas burners and demolition of the specialized building.
    • Supply, installation, and commissioning of two new residual biogas burners.
    • Design works (preliminary and main project), construction works, automation integration, and audits.
  • Technical requirements:
    • Burners must have a capacity of at least 550 m³/h.
    • Integration…
       
      To see full summary, please log in or register.
t

👋 Hello! I am TEDAS – your procurement assistant 💼✨

What would you like to know about this procurement?

Note: This is preliminary information. For accuracy, please review all procurement documents.
Ask your questions here...

310481_alltoovotjate_kontrollimise_tingimused.pdf

310481_hindamiskriteeriumid.pdf

310481_korvaldamise_alused_ja_kvalifitseerimistingimused.pdf

310481_vastavustingimused.pdf

310481.zip

Lihthankemenetluse kord.docx

Lisa 1 Ehitus- ja paigaldustööde üldtingimused 1012025.pdf

Lisa 1 Jääkbiogaasipõletamise sõlm (2).pdf

Lisa 2 Jääkbiogaasipõletamise sõlm.pdf

Lisa 2 Müügilepingu üldtingimused.pdf

Lisa 3 PID skeem.pdf

Lisa 3 Tehniline kirjeldus Jääkbiogaasi põletamise sõlme rekonstrueerimine, TK 27042026.docx

Lisa 4 Pakkumuse maksumuse vorm 2x550.xlsx

Lisa 4 RPJ biogaasi koostis 14.04.2026.pdf

Lisa 5 Gaassikella põletite süttimiskõrgused.pdf

Lisa 5 Töötervishoiu-, -ohutuse- ja keskkonnanõuded AS Tallinna Vesi (30012026).pdf

Nõusolek vahenditele tuginemiseks.docx

TK lisad.7z

Töövõtuleping.docx

Ühispakkujate volikiri.docx

Ready to get started?

Subscribe and enjoy all the benefits every day!