Supply and installation of cable joints for Avinurme substation AI

TEDAS your procurement assistant

Ask a question about this procurement

t

Subject of the procurement

  • Object: Supply and installation of cable joints for Avinurme substation.
  • Technical requirements:
    • 35 kV: 3 pcs AXLJ-TT 1x150Al+35Cu mm2 (indoor installation, ABB ZX1.2 switchgear) and 3 pcs AXLJ-TT 1x150Al+35Cu mm2 (outdoor installation, transformer T1T busbar).
    • 10 kV: indoor termination connectors AHXAMK-W 3x240Al+35Cu mm2 (10 kV switchgear) and outdoor cable terminations AHXAMK-W 3x240Al+35Cu mm2 (auxiliary transformer T1T busbar).
  • Location: Enefit production units in Ida-Viru County (EE00A)…
     
    To see full summary, please log in or register.
t

👋 Hello! I am TEDAS – your procurement assistant 💼✨

What would you like to know about this procurement?

Note: This is preliminary information. For accuracy, please review all procurement documents.
Ask your questions here...

310916_hindamiskriteeriumid.pdf

310916_korvaldamise_alused_ja_kvalifitseerimistingimused.pdf

310916_vastavustingimused.pdf

310916.zip

Juhised pakkujatele väikehankemenetluses RHR.pdf

Juhised pakkujatele_VH.zip

Läbirääkimiste läbiviimise kord väikehankemenetluses ja lihthankemenetluses.pdf

Liisuheitmise_kord RHR.pdf

Lisa 1.pdf

Lisa 2.jpg

Lisa 3.jpg

Tehnilised tingimused.docx

Tehnilised tingimused.zip

Tööandjate vastutuse ja kohustuste jaotus töötervishoiu ja tööohutuse tagamisel.pdf

Töövõtulepingu_projekt.zip

Töövõtulepingu üldtingimused_EST.pdf

Töövõtulepingu_vorm.docx

Vorm_Lepingute nimekiri.docx

Ready to get started?

Subscribe and enjoy all the benefits every day!