Object of Procurement

  • What is being procured: Purchase and installation of two flue gas measurement systems at the Iru power plant.
  • Main technical requirements, features:
    • Two existing Combiprobe CP100 measurement systems are to be replaced with two new equivalent measurement systems.
    • New devices must achieve a measurement accuracy of no worse than 2%.
    • Must include an analog output of 4-20 mA.
    • Must enable the transmission of measurement data…
       
      To see full summary, please log in or register.
t

👋 Hello! I am TEDAS – your procurement assistant 💼✨

What would you like to know about this procurement?

Note: This is preliminary information. For accuracy, please review all procurement documents.
Ask your questions here...

295898_hindamiskriteeriumid.pdf

295898_korvaldamise_alused_ja_kvalifitseerimistingimused.pdf

295898_vastavustingimused.pdf

295898.zip

Hanke alusdokument (RHAD)_295898.docx

Lisa 1 Tehniline kirjeldus_295898.doc

Lisa 2 Lepingu tingimused_295898.docx

Lisa 2 lisa 2 Toovotulepingu_uldtingimused_est.pdf

Lisa L2. Kasutusjuhend/Combiprobe CP100 master view.jpg

Lisa L2. Kasutusjuhend/Dusthanter SP100.pdf

Lisa L2. Kasutusjuhend/Dusthunter SP100.jpg

Lisa L2. Kasutusjuhend/Flowsic 100.jpg

Lisa L2. Kasutusjuhend/FlowSIC100.pdf

Lisa L2 Kasutusjuhend.zip

Vorm III Pakkumuse kirjeldus.docx

Vorm II Pakkumuse maksumuse arvutamine.xlsx

Vorm I Taotlus hankes osalemiseks_295898.docx

Ready to get started?

Subscribe and enjoy all the benefits every day!